19-09-17 Pool electrics and equipment installed
13-09-17 Pool & alfresco pavers laid
11-09-17 Pool pavers screed laid
08-09-17 Pool surround pavers and equipment slab concrete laid
23-08-17 Pool coping and tiling finished
10-07-17 Pool concreted
27-06-17 Steel work
22-06-17 Pool excavated
21-06-17 Pool peg out
13-03-17 Pool contract signed
24-03-16 Maintenance Inspection
17-03-16 Landscaping phase 1 started
10-03-16 13 week Maintenance Issues List submitted
05-01-16 Driveway sealant redone – again
28-01-16 Driveway sealant re-done
20-01-16 Driveway spray coated & sealed
11-12-15 Handover
03-12-15 NBN
01-12-15 PCI
27-11-15 Fly screens & doors in
27-11-15 Driveway saw cut
26-11-15 Carpet fitted
26-11-15 Driveway poured
25-11-15 Rain garden corrected
23-11-15 Driveway formwork
18-11-15 House clean
14-11-15 Cooker Hood fitted
14-11-15 Door furniture & bathroom fittings
13-11-15 Air con
11-11-15 Painters back to finish
09-11-15 Walls made good
07-11-15 Glass splashback fitted
05-11-15 Master robe, WIP & Cloak fit out
04-11-15 Tilers finish main floor
02-11-15 Tilers start main floor
30-10-15 Shower screens & mirrors fitted
20-10-15 Baths, toilets, taps & shower rails installed
19-10-15 Main floor tiles delivered
16-10-15 Rain Tank installed
16-10-15 Electrical fit off
14-10-15 Store, linen, Bed 2, Bed 3 & 4 WIR wire shelf fit outs
09-10-15 Acid wash bricks
08-10-15 Tilers back for wet areas
29-09-15 Benchtops in, sinks and basins in
25-09-15 Painting starts
19-09-15 Tiler starts wet areas
18-09-15 All wet area cabinetry in
18-09-15 Waterproof inspection passed
17-09-15 Gas connected & tiles delivered
14-09-15 Kitchen & Butler’s in
14-09-15 Waterproofing
11-09-15 Cabinetry delivered
08-09-15 Doors on & Lock out
07-09-15 Garage door
04-09-15 Staircase
03-09-15 Cornice
01-09-15 Progress Payment 20% Commencement of Linings
26-08-15 Gyprock
25-08-15 Lower eaves completed
20-08-15 Independent pre-lining inspection
18-08-15 Insulation
17-08-15 Gas fireplace fitted
15-08-15 Lower downpipes fitted
14-08-15 Electrical rough in
12-08-15 Air Con
12-08-15 Lower roof Colorbond
01-08-15 Lower roof fascia & guttering
29-07-15 Scaffolding removal & re-erected for Alfresco roof
24-07-15 Wisdom Landscaping meeting on site
09-07-15 Progress Payment 20% Bricks
07-07-15 Acid wash first floor bricks
02-07-15 Colorbond main roof on
25-06-15 Colorbond roof & sarking delivered
22-06-15 Guttering & fascia delivered
12-06-15 Progress Payment 20% Frame
11-06-15 Scaffolding erected
03-06-15 GraniteGuard termite protection
02-06-15 Houspect framing inspection
02-06-15 Bricking commences
01-06-15 Bricks delivered
27-05-15 Framing finished
19-05-15 GF frames up
16-05-15 Framework delivered
13-05-15 Progress Payment 25% Slab
08-15th Storm water drains completed
05-05-15 Power pole re-sited
05-05-15 Houspect slab inspection
02-05-15 Slab laid!
01-05-15 Waffle pods & reo laid
30-04-15 Internal Plumbing
29-04-15 Piering & form work
08-04-15 Site Fencing & scrape
01-04-15 April Fool’s Day – the portaloo!
26-03-15 File passed to Production Estimating team
Admin complete
19-03-15 Bank mortgage approved
02-03-15 End Panel signed off
26-02-15 End Panel issued
23-02-15 Construction plans signed off
16-02-15 Construction plans issued
11-02-15 Site pegged
30-01-15 Signed off Draft End Panel
16-01-15 Draft End Panel received
14-01-15 CDC compliance checked
09-01-15 TECK approval
19-12-14 CDC Approval
18-12-14 Submitted for CDC approval
03-12-14 updated Wisdom landscape plans accepted
25-11-14 CDC plans – final version
20-10-14 CDC plans – version 1
16-10-14 BAL Risk Assessment
02-10-14 Land settled
25-09-14 Mortgage signed & sealed
23-09-14 Timpelle kitchen plans accepted
19-09-14 Wisdom Landscaping quote accepted
17-09-14 Land registered
05-09-14 Di Lorenzo carpet & tile quote accepted
01-09-14 Land surveyed
18-08-14 Clipsal electrical
18-08-14 Di Lorenzo tiles appointment
15-08-14 Air con appointment
13-08-14 Timpelle kitchen appointment
13-08-14 Internal/external colours appointment
13-08-14 Wisdom Landscaping
11-08-14 Contract signed
07-08-14 Plans v3
04-08-14 Plans v2
14-07-14 Tender v7
11-07-14 Tender v5 & v6
02-07-14 Tender v4
05-06-14 First set of plans
01-05-14 Tender accepted
26-04-14 Tender v3
15-04-14 Tender v2
07-03-14 Tender Presentation
08-01-14 Request tender from Wisdom
20-12-13 Wisdom deposit paid
04-10-13 Gardener’s Ridge land deposit paid
14-09-13 Gardener’s Ridge land reserved
September 25, 2014 at 19:53
Your kitchen plan looks great. I’m guessing there’s a good reason that you don’t reduce your bench length 1-2 cm to avoid the join in the Caesarstone??
September 26, 2014 at 11:37
Thanks Johanne, the bench length is 18cm longer so I don’t really want to trim that much off. Hopefully the stonemason will do a good job with the join. I’ve looked at joins in different Builder’s show homes, some are brilliant and some are awful. Here’s hoping ours is great – one slab of beer coming up….
September 26, 2014 at 11:55
My mistake, sorry. I read the bench length as 3.01 instead of 3.1.
September 26, 2014 at 12:45
I did exactly the same thing before and wondered why he didn’t add a filler to stop the join 🙂 I also phoned Caesarstone to double check the slab sizes.
September 27, 2014 at 17:59
Your kitchen looks fab! Sounds like a custom design? I’m curious how flexible Wisdom Homes are in regards to customizing the kitchen? Did you make a lot of changes from the standard layout?
I’m having sleepless nights over our kitchen/butlers pantry re-design at the moment. I’m so tempted to just forget about making any changes and just stick to the standard as it’s pretty good already. But then again this is supposed to be our dream home with the dream kitchen!
September 28, 2014 at 16:17
Thank you 🙂 the kitchen layout is only a little different from the Wisdom Standard, mainly no slot in cooker but a built in double oven plus additional cupboards behind the sink run. However we have upgraded the finish & the Caesarstone plus put in two more sets of pot drawers. I thought their design was pretty good. We have done a custom design in the Butler’s though as standard is three walls of shelves. I’m pleased as its my design and I can’t wait to see it for real 🙂 so all in all Wisdom were very flexible provided you’re happy to pay for it.
Good luck with your design!
April 19, 2019 at 22:55
I really appreciate your work, especially its experienced part that made it easy to understand the whole point. Thanks for sharing such a great post.